Skip to Content
0
Feb 14, 2011 at 08:55 PM

time based inspection

274 Views

The material once produced goes to oven and will be kept in oven for few hours. For example material A can be kept in over for 6.5 hours, Material B u2013 5.5 hrs, and C can be kept for 6.0 hours.

When the material is pull out of oven before specified time then system then system should not allowed user to move the stock out of the oven. Stock when entering the oven will be un-restricted.

My thought is to create an inspection lot when material is moved into the oven (08 -Inspection type). When results entered is validated with the time in which material moved into oven. And check if this time is less than required material time.

I am not sure where to capture hours for the material and how to do validation of result entered with time which material moved to oven.

Client don't want to create production order for this process.

Is there a standard way to do map to SAP. ? ?

Please adviceu2026

Thanks

S