Former Member
Feb 14, 2011 at 04:13 PM

Profiles

43 Views

Hi,

I have an issue in understanding the way the profiles work.....kindly clarify

For example

I am planning in weekly buckets

In the Planning book the bucket shows as start on MON and end on SUN ---so it is Feb14th to Feb20th

There is a requirement on Feb 16 ie wed

But the demand was shown to be falling in the previous bucket in the product view.........this issue is causing a lot of disturbance in the capacity calculation. The demands are falling in the previous bucket in the product view and resources are getting overloaded

Kindly helo me fix this

Thanks,SS

Edited by: SAPSriman on Feb 14, 2011 5:14 PM