Both procurement types with repetitive manufacturing

90 Views

Hello Experts,

I have a problem with a material and I am not sure about what is the best way to solve it. I have a material that initially was a purchasing material and was defined like:

- Procurement type: External procurement.

- Price control: Moving average price/periodic unit price

Now, because of the plant capacities, it is possible to produce this material too, depending on the necesities. This means that the new procurement type for it will be both procurement types. The problem is that in this plant the manufacturing strategy is Repetitive Manufacturing, but the price control should continue being moving average price.

Is it possible to have a repetitive scenario with a moving average price? the solution is in this case correct? Should I define any different information for this material?

Thanks in advance.

Laura