Hi ,

I want your input on following scenario.

I am using REM.

There are 2 different departments which look at production and consumption of semi and finished products.

Example to produce ' A ', b and c (semi finished products ) are required.

The FG department which looks after product A cannot book the consumption quantities for b and c.

If i go with REM backflush(GR of finished product A), then i have the option to make the quantities for b and c as zero at time of posting but there is chance of error from users

What can be the best way forward to resolve the issue.

Regards

ShankarR