on 02-14-2011 5:20 AM
Dear Gurus,
for a material have setted following parameters:
MRP Type: VB
ROL:10
SAFETY STOCK:5
LOT SIZE:HB
MAX LOT SIZE:200
wheu we run theMRP ,system consume safety stock we do not want to consume safety stock.
please advise for setting
siva
Hi Siva,
Ur rerquirement is still not clear to us.Kindly elaborate
When we consider reorder level planning Safety stock has less meaning as it is part of reorder point e.g.Reorder poing is 1000 and safety stock is 50 .Then system will always check stock reorder till 1000 and not 1050 i.e. aditional safety stock is not considered
Cheers
Vishal...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
suppose i have stock 100 ea, satety stock is 10 ,avialable qty : 90,now for a prodcution order if requirment qty isa which is 100
system is consuming 100 ea it is not lefting 10 ea which is safey stock
my requiment is system shold consume 90 ea for remaining 10 ea it should create proposal.
siva
Hi there
You are using the Lot Size HB,, in this sytem will check the "Maximum stock level"** since it is 100, system picking that value and providing the procurement proposal as 100 even though you have stock 10,,
use the Lot size EX, sytem will work as you want ( Procurement proposal for 90)
Hope it helps
Thanks
Senthil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.