on 02-13-2011 9:36 AM
Hello Friends,
I am searching for job and went for interview in Wipro. They asked me the difference between Planned, Actual and target cost..... I tried to search on Google and SAP Blog's but couldn't find the appropriate or understandable answer yet, So it would be great if you you can guide me a bit on this......
Thank You,
Hi dear,
Sincerely advicing you not to mention the history or why you are asking this question.
Total Plan Cost = Std Cost the material required to Produce X Planned Qty of the required material
Target Cost = Std Cost the material planned to Produce X Std Qty of material required to produce, for Produced Actual Qty
Actual Cost = Std Cost the material planned to Produce X Actual Qty of material consumed, for Produced Actual Qty
For Example : Final Material - A,- Qty Planned to Produce - 2 nos
As per Standards, Below Qty of Materials required to Produce A , for 2 Nos
Mat B - 2Nos X INR 50 = INR 100
Mat C - 4Nos X INR 60 = INR 240
Activity Cost = 2 hrs X INR 10 = INR 20
Total Plan Cost = INR 360
Actual Qty Produced = 1 No
Actual Consumption is as follows .
Mat B - 1.5 Nos ( X INR 50 = INR 75 )
Mat C - 2 Nos ( X INR 60 = INR 120 )
Activity Cost = 2 hrs ( X INR 10 = INR 20 )
So, Actual Cost = INR 7512020 = INR 215
Whereas, Target cost for the Actual Qty ( of Product A - 1 Ns) is , as follows,
Mat B - 1 Nos ( X INR 50 = INR 50 )
Mat C - 1.5 Nos ( X INR 60 = INR 90 )
Activity Cost = 1 hrs ( X INR 10 = INR 10 )
Therefore, Target cost = INR 509010 = INR 150
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Friends,
Thank's both of you..... I got the point and understood all the things in costing.
You have helped me a lot to solve this issue.
Regards,
Mayank
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Rahul,
I really do not understand why B=1 and C=1.5 (as follows statement)?
Whereas, Target cost for the Actual Qty ( of Product A - 1 Ns) is , as follows,
Mat B - 1 Nos ( X INR 50 = INR 50 )
Mat C - 1.5 Nos ( X INR 60 = INR 90 )
Activity Cost = 1 hrs ( X INR 10 = INR 10 )
Therefore, Target cost = INR 509010 = INR 150
Could you please help to explain it in detail?
Now I got problem how the target cost caculate...>"<
Thank you a lot.
Ella
Planned cost:- system will take the price based on price control In a material master and multiply with per FG and Component quantity with respect to the production order
Actual cost : system will take the price based on price control In a material master and multiply with actual goods movement qty of the material with respect to the production order
Target qty: system will take the price from standard cost estimate - IF you not run the std cost estimate, system won;t uodate the target cost in production order
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.