on 02-13-2011 7:22 AM
Hello All,
I want to have a text field on the screen for Collective Confirmation (transaction co12).
Is there any way to have it, through configuration or exit.
Thanks
Hi dear,
Without touching SPRO or using exit you can maintain the long text in CO12.
1) After entering the production order number and operation number press enter and select the entire line now click on detail view icon (it is located at the bottom of the screen and to the left of Goods movement icon) you can maintain the long text in the screen opened after ckicking details view icon.
2) Alternatively you can confirm the operation by CO11N for this go to OPK0->Area selection->Detail areas->Select the option of confirmatioin text and give some name for push button text. Here you can maintain the text.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
9 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.