Routings

31 Views

Friends,

Firstly I maintained LATHEMAC as work center in routing and set up time 10 min. & m/cing time 30 min. After that I maintained LABOUR01 as work center & the labour time in 50 min.

but in graphical representation system is not considering time of LABOUR01- 50 min. Why?

(Also I maintained parameters of labour in work center as ' to be entered'.

Pl.guide