Production Order reservation(ETO) not deleting after PGI (VL01N)

101 Views

Hi All,

Greetings!!!

A query, regarding ETO (Project system)

ETO scenario, For production, reservation will be create through WBS element. After production , If I do delivery and PGI, production order reservation is not deleting.

Same material If I do delivery(LP) through CNS0, then order reservation is going to delete after PGI. But Sales order price is not copying to Billing If I follow this process.

Is there any copy controls to flow the sales price to billing when delivery happens through CNS0. If not

Which requirement class and movement type I need to determine in Sales order.

Please do needful.