Dear All,
Require your help on this.
I have a Project Definition where we have Multiple WBS (upto level 2) and we are using single network.
Activities are distributed in various WBS levels (Lowest WBS).
For example I have WBS where there are three activities, and two activities have status CNF, and one activity has status PCNF (Partially confirmed)
When I re-schedule the project the Early start date of the Partially confirmed activity is getting transferred.
Ideally the Early start / Actual start of the CNF activity should be transferred to the WBS level.
Due to this when I "determine actual dates" @ WBS level, it gets over written after scheduling.
For WBS I Re-schedule using Top Down ; Forward in time ; WBS determines dates
For Network I Re-schedule using Strict bottom up ; Backward in Time ; Network Determines Dates
I have ticked Adjust Basic dates & Start in PAst 999 ; but still the Actual start dates of confirmed activities are not transferred.
Please help me