Hi masters

I trying send PO in XML to SUS through XI ,

but when try to send the SRM/EB system show the next message

Processing BBP_PO_SEND_XML Is Started

An SLD system has not been assigned to logical system

Action could not be successfully executed

in XI system I defined the SLD sistem for SRM/EB and SRM/SUS

that SLD name is settup into define system Landscape into colum System Land Directory Name

in SLDCHECK all is Ok on green light.

what can I do ?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Oscar,

In your SRM system, go to SPROSRM ServerTech Basic Settings--Define System Landscape.

Here, assuming you have defined your connected systems, provide the Business System name created in SLD under the field 'System Landscape Directory Name' for both SRM & SUS.

Regards,

Nikhil

Former Member
0 Kudos

thanks Nikchil.

How commented the Names of Business Systems created in XI SLD are settup in into System Landscape Directory Name but problem is persistent.

What can i Do ?

Former Member
0 Kudos

Hi Oscar,

In your SLD, pl check if the Business Systems created are assigned to logical systems. For example if the BS for SRM client 100 is BSSRM100, then check if this BS is assigned to SRM client 100 in SLD.

Regards,

Nikhil

Former Member
0 Kudos

Thanks Nikhil

into SLD you have the reason because in Business System have not Logical System added.

I was add the system Logic to SRM server into Business System but the problem persist .

Is necessary clear buffer or other something else.

Former Member
0 Kudos

Oscar,

Is the SLDCHECK successful from your source system? Also ask your Basis team to set up XI properly especially the SLD (BS creation, software components, technical systems etc)

Regards,

Nikhil

Former Member
0 Kudos

Hi. Nikhil.

In SRM/EB

1.- trying configurates SMXB_ADM

2.- Integratio Engine configration

3.- Role of Business System = Application System

4.- Corresponding Integ. Server = dest://RFC type H for XI system,

problem .

when I push bottom check (F7)

the message is the next

red light No access to system Landscape at present

Former Member
0 Kudos

Dear Nikhil .

the problem was resolved . the problem was into SLD the Business System . a created again the Business System , clear the Cache and working ok.

thanks .

Answers (1)

Answers (1)

masa_139
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi,

Please check "Define System Landscape" customize in SRM. You need to define SRM and SUS logical systems and Business System names which are defined in SLD.

Regards,

Masa

Former Member
0 Kudos

Thanks. MASA.

the SLD Name into Customize are defined the Name of Business Systems Names created in XI SLD but the problem is persistent

what can else revew to fix the problem.

thanks.