Dear Gurus,

I am running the MRP for a material (ECC 6.0) which has:

1. MRP Type: PD

2. Lot Size: PK (Periodic Lot size according to planning calendar)

3. Rounding Values: 12

And the MRP is not respecting my planning calendar.

I have deleted the Rounding Value and it respected it properly.

From what I see in MD04 the system try to finish the stock before creating a new purchase requisition/planned order, so when the stock is finishing it creates one without respecting the calendar.

Is this normal behaviour of Lot size PK or should I place a note to OSS?

Kind regards,