Dear Gurus,
I am running the MRP for a material (ECC 6.0) which has:
1. MRP Type: PD
2. Lot Size: PK (Periodic Lot size according to planning calendar)
3. Rounding Values: 12
And the MRP is not respecting my planning calendar.
I have deleted the Rounding Value and it respected it properly.
From what I see in MD04 the system try to finish the stock before creating a new purchase requisition/planned order, so when the stock is finishing it creates one without respecting the calendar.
Is this normal behaviour of Lot size PK or should I place a note to OSS?
Kind regards,
Federico