Resource - no capacity profile

Hi Experts,

we ciffed the resources from R3, but in the resource we don't have any capacity. If we execute the /SAPAPO/REST02 there aren't inconsistencies, but if we go to the timestream ID, there is no capacity for the resource.

We are using a standard calendar 01, and already execute the report /SAPAPO/CRES_CAPACITY_LENGTHEN but any capacity appears at the capacity profile.

Anyone faced such issue?

Thanks in advance

Thiago Cyrillo

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Feb 10, 2011 at 11:48 AM

    HI,

    As you are cifing the resources from ECC, these resources will have external capacity tick mark in resource master /sapapo/res01. As these are external resources you have to define shift's and intervals in ECC in resource master.

    At the same time plz check the factory calender validity (SCAL) which was defined in APO. If the calender is not valid then you will not be able to create order. once you maintain the above said, try creating the order.

    Thanks & Regards

    Sravan maturu

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Sravan,

      the problem was in the factory calendar.The factory calendar was valid until 2010.

      Thanks for help

      Thiago Cyrillo

  • avatar image
    Former Member
    Feb 09, 2011 at 10:33 PM

    Hi Thiago,

    1. You should have maintained capacity for the resource in the R/3 system & transferred the Resource master data.

    2. /SAPAPO/REST02 just check if there is any inconsistency in the resources availble in APO.

    3. /SAPAPO/CRES_CAPACITY_LENGTHEN is used to activate the resource horizon for loading.

    Please check if the resource exit in APO system. In normal circumstances, the resources are not CIFed to APO if no capacity is maintained in R/3.

    Please maintain the capacity for the resource with start time , endtime and break (as per the business requirement) and re-transfer the data. Execute RIMODINI to initial transfer.

    Hope this helps.

    Regards,

    Nawanit

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Nawanit, thanks for the reply.

      All the capacity data are maintained in the R3 system, and CIFed to APO.

      The problem is that there is no capacity profile for the resources, and we cannot create planned orders inside the resource planning horizon -30 +180.

      Regards

      Thiago Cyrillo