on 02-09-2011 11:03 AM
Hi Friends,
I have 2 production orders. One is belongs to semifinished and one is belongs to finished level.Both orders confirmed and do the goods recipet.But i want to cancel the order.
So i am going through co13 .it is not working for semifinished level.for finished systm accepted. but when i saw the document list it showing only 101 m.ty.when i was cancel the order system needs the 102 m.ty.
Please tell me where i done the wrong.
Venkat
Dear Venkat,
Have you issued the SFG to FG?
Then:
1.Revoke the teco(if done),then do resturn delivery for the FG material using MIGO and cancel the confirmation using co13.
2.Next,cancel the GI of SFG to FG material.
Repeat the steps 1 and 2 for the SFG order.
Regards,
Joseph Charles Vaikathussery
Edited by: Joseph Charles on Feb 9, 2011 4:39 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.