on 02-09-2011 9:35 AM
Hello Experts
U stock materials (Serviceable ) should consider material for MRP and not for availability check in PM orders
We have solved the problem by settings in the customizing in PP that we are able to set the materials at stock U location (serviceable )should not be considered in Mat Availability for PM orders
Settings we have made for all storage locations in U * By excluding storage location stock from MRP
If storage location stock is excluded from MRP at plant level, no receipts for this storage location will be created in the MRP planning run.
so we are able to run the availability check perfectly
But now MM dept.is not accepting this as they want this stock to be considered for MRP
Has anybody done this scenario successfully please reply the solution
In short we want stocks of Materials at U serviceable location should not consider for Work order material Availability check
But at the same time it should consider stocks of Materials at U serviceable location for MRP run what is way to do this
Regards
Pratap
A way that I think of, is to set the ATP at SL level, so in PM order you check only in a specific location, not in all the plant.
Of course that you need to let all SLs to be relevant for MRP, otherwise this stock is not considered for planning.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.