on 02-08-2011 5:28 PM
Is it possible to add a operation to the production order which is released and partially confirmed?
Requirement:
In a typical production process, total 5 operations are utilized. But due to one particular operation (Opr.30 -
filling) did not happen properly, which results in having additional operation (reheating), which needs
to be accomodated.
How to map the above process in SAP
Add manually the reheating operation In co02 in operation overview,