Feb 08, 2011 at 03:46 PM

Process orders scheduling dates do not match

306 Views

Hi PP gurus

I have a customer order that must be delivered the 25th of feb, This material is produced in house, in Material Master in MRP 2 View I have mantained inhouse production time as 3 days, and GR Processing time as 1 Day

When I run MRP I get the finish date of the planned order the 24th and start date the 21st This is fine, but when I double click this planned order a little window pups up and when click the "Convert to process order" button its giving start date and finish date as 23rd of Feb Why is the system adding an extra 2 days ??

I am running MRP with scheduling 1: Determination of basic dates for planned

Thanks in advance