Link between Progress and Consumption

Dear Sir,

I want to link between project progress and consumption.

Means we get work for testing of no. of joints say 1000. Now I want to make some restriction say for testing of 10 joints , only 100 qty of this material shud consumed. System should triger some message that I am exceeding my allocated amount.

Please help the needful

Regards

Umesh

Add comment
10|10000 characters needed characters exceeded

3 Answers

  • Posted on Feb 07, 2011 at 01:55 PM

    Hi,

    It seems you need to control actual cost posted against a WBS element based on the project progress.

    Use some exit to put a validation as system should not allow to post actual cost based on the project progress or BCWS.

    Tnx.

    Abdul.

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Feb 08, 2011 at 05:19 AM

    Dear Sir,

    As per my knowledge also their is no std available in SAP.

    I have a solution that make no. of joints as an activity which will get confirmed on daily basis. At the same time actual consumtion I will get from CJI3.

    So do analysis of both the reports to fullfill the requirement.

    Any other solution exist ?

    Regards

    Umesh

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Umesh,

      thats right.

      Doing analysis at user level is always possible.

      Establishing system control is not possible.