my company is using a Z - MRP type which has the following settings:
MRP procedure = D - Material requirements planning
Forecast Indicator = No Forecast
Consump.ind.forecast = G - Total consumption
MRP ind. forecast = G - Total requirements
Even though we have a Forecast Indicator set to "No Forecast", materials with this MRP type are forecasted every month. We then get some issues with requirements that are required.
Does anyone know what settings we should have in order to avoid Forecasting being run on materials with the MRP type above?
Thanks for your input:-)
Br,
Lars
Dear,
Prerequisites: Transaction OMDQ
MRP type with
Forecast indicator <> ' ' (that is, for example, * for optional forecast) (PROKZ)
MRP indicator of forecast = ' ' (that is, 'Not to be included in planning') (PROOS)
If the MRP indicator = ' ', the forecast requirements should not be involved in the MRP run
However, forecast requirements are only considered if the "MRP indicator of forecast" is set in the MRP type.
Also check the OSS note 369673 .
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
by setting the MRP ind. forecast = ' ' (Not to be included in planning) the forecast can run, but the forecast result is not taken into consideration during planning (MRP run).
Of course, these settings are logical and makes sense to an expert, but we just did not see the link between the settings
Once again, thanks for your input and guidance!
Br,
Lars
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.