start of cycle date is not taking while scheduling

Former Member
0 Kudos

Hi

I have created a maintainance plan with scheduling indicator TIME and scheduling period 365 days . I am giving start of cycle date as 04-02-2011 but while scheduling the plan it is taking 19-02-2011 as first plan date . my maintainance plan cycle is 15 days.

I want that date as 04-02-2011 . how can I get that.

Regards

Kumar

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

thanks its working fine and sorry for the delayed responce

0 Kudos

The system is working fine. Once you decide the start cycle date then first plan /Order will come only after the cycle duration from the start cycle date. You can put 15 day before date from 4-2-2011. then you will get first call on desired date.

Raj

Former Member
0 Kudos

Put back date 21.01.2011