on 02-03-2011 11:45 PM
Dear experts ,
I am executing discrete optimization but it is not taking lot size and rounding value into account. On SNP PDS i am using minimum lot size 1 but on product master i am using 200 and rounding 20 , but optimizer is creating planned order with 180 pc. ..... Someone can help me please.
Regards Mauricio
Hi
A couple of quick checks:
Have you activated the control of lot size constraints on the "General Constraints" tab page in the SNP optimizer profile?
Is the value for the plan explosion set to 5 Production Data Structure Generated from R/3 in the location product master (tab page PP/DS) in SAP SCM?
regards
Ian
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi lan ,
Yes on master data the value is 5 and on general tab i am using Maximun PDS Lot Size and on discrete constraint i am maintaining days for minimun PDS lot size and integral PDS.
In product master data i am using Lot-for-lot . But still not working.
Please help me with this issue.
Thanks in Advance