Dear all,
Before explaining in more detail my issue, I would appreciate your help clarifing one doubt.
1) In SD customizing we can assign Factory Calendars at the level of:
Sales Organization
Plant
Shipping Point
Route,
Could you explain which information is affected by each of thesel assignments?
2) My issue at the moment is the following: Customer does not want that the Confirmed Date falls on Saturdays and Sundays.
Taking into consideration that I have two Factory Calendars:
Calendar A (includes weekends)
Calendar B (excludes weekends)
In which of the abovementioned setups should I assign the calendar B in order that if the confirmed date is not on weekends?
Many thanks for your help.
Kind regards
Fátima
If possible Sales Org
Plant
Shipping Point
Route
Thanks for your help.
Fatima