on 02-02-2011 1:29 PM
Hi,
We have a schedule agreement with firm zone maintained and MRP binding indicator blank is maitained in additional data at item level. But we have seen schedule line quantity has been changed after MRP run. I dont understand how its possible....please help
Regrds,
Raghu
Hi Raghu,
do You still have the * at MD04 at the related lines? Check out OSS note 204153
Br
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If the qty is not transmitted to the vendor using message transmission, system does not firm the qty with in planning time fence.
So pls chk your planning time fence as well.
Also pls chk the below link
http://help.sap.com/saphelp_46c/helpdata/en/f4/7d2a5b44af11d182b40000e829fbfe/content.htm
BR,
Krishna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Krishna,
We use MRP typr PD, so PTF is not required and more over the quantity is already transmitted to the vendor.\
i dont understand how the quantity has been changed??? are there any other indicators which will result in schedule line quantity change in MRP run even if firm zone and MRP binding indicator is maintained...
Please suggest.
Regards,
Raghu
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.