PO values in budget related reports

38 Views

Hi,

I am creating PO from ME21N and asigning WBS as account assignment. I can see this PO value as commitment in cost element report S_ALR_87013542 but I see this value in Assigned orders in budget report S_ALR_87013558. I don't have any issue from availability control but why I am not seeing this cost against committment.