on 02-02-2011 10:05 AM
We are building a new box/system, and have now got to the PRD box stage. Unfortunately, the substitution rule in PRD does not appear to be working, and when we add a sales order item, it determines profit centre as DUMMY
I have checked the following matches to QAS.....
0KEM - The substitution rule
0KEL - The link to SD
KE52 - The profit centre master data, and that they are active
If I put simulation on, I can see the rule is accessed and that my expected step is true, but it still comes back with dummy.
Are theere any checks I've missed?
Is there anything on the Sub riule side I need to "Activate" in the PRD box?
Any advice appreciated.
Graham
Hi,
At time of sales order the profit center can be set by
1. CO account assignment (strongest option)
2. Manual entry
3. PCA substitution
4. Material / plant (weakest option)
So if the sales order has account assignment to say a PA segment which contains PRCTR = dummy then that will get preferance over the value from substitution.
regards
Waman
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Waman, I think you've cracked it.
The PC on the account assignment field is set as Dummy, this is comming from the WBS, where its blank.
We had set this as mandatory, but were using a diff profile for cut-over projects, and I think it hasn't been set in there.
I'll fix this and re-test
Thank again
Graham
Hi,
Cheak Your Material Master Profit Centre Field
Check Transaction code -3keh if and okb9
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Check 0KEM if the substitution rule is active for your contr area
BR,Ajay M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ajay
Can you give any more information, like a transaction code or IMG path. I thought I'd looked everywhere, and can't see any obvious activate nodes.
I've looked through the controlling and enterprise controlling areas.
The only activation I have found so far, is in 0KEL, which matches our the settings in our QAS system.
Thanks
Graham
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.