Hi Experts,
I am working on a solution regarding to GOA in SRM - Contract in ECC creation and i am wondering about the following scenario:
Create 1 GOA in SRM 5.0 for a central/global purchasing organization and when the appropriate BADI going to transfer it into ECC, it creates contracts for all company codes.
At my current client they use GOA but until now they created 1 GOA for a specific p.org and the BADI transferred (and created) contract in ECC for the specific company code (they donu2019t have kind of central/global purch organization unit in ppoma). In the future they would like to create GOAs which are usable for all companies, but instead of creating (and changing) them manually (N GOA in SRM for N contract in ECC) they want to have an automatism.
Does any of you have any experience on this? That would be really good if you can share with me some high level overview about concept.
Thanks in advance for your help!
Best Regards,
Attila