Hi all,
We are using CTM planning scenario.
After CTM planning, the operations in a planned order are scheduled as per the capacity available at
resource for each operation. So there is may be a gap between end time of one operation and start time of
the successive operation which is as expected.
Now the issue is:
In ECC, when the planned order is converted into production order, it is eliminating the time gaps between
operations and next operation is started immediately after end time of the preceding operation.
This is happening even after converting planned order into production order using conversion indicator in
APO.
The requirement is, in ECC, system should keep the operation times as scheduled in APO.
Please let me know if any details required.
Regards,
Yogesh
Hi,
Can you check the " Scheduling parameters for production orders" defind in ECC under Adjust scheduling tab
the the various options defined.
Also enable the scheduling with breaks indicator and see whether you get the proper results.
Thanks,
nandha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.