Regarding prod order operations scheduling

Hi all,

We are using CTM planning scenario.

After CTM planning, the operations in a planned order are scheduled as per the capacity available at

resource for each operation. So there is may be a gap between end time of one operation and start time of

the successive operation which is as expected.

Now the issue is:

In ECC, when the planned order is converted into production order, it is eliminating the time gaps between

operations and next operation is started immediately after end time of the preceding operation.

This is happening even after converting planned order into production order using conversion indicator in

APO.

The requirement is, in ECC, system should keep the operation times as scheduled in APO.

Please let me know if any details required.

Regards,

Yogesh

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Jan 31, 2011 at 08:45 AM

    Hi,

    Can you check the " Scheduling parameters for production orders" defind in ECC under Adjust scheduling tab

    the the various options defined.

    Also enable the scheduling with breaks indicator and see whether you get the proper results.

    Thanks,

    nandha

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      hi Nandha,

      I have tried with those options but the results are still the same. Its not taking operation times from APO.

      Regards,

      Yogesh