Dear gurus,

could anyone explain me

*Loading date

*Delivery Date

*Goods Issue Date

*Material Available Date

*Transportation Planning Date

and effects of them on the system

and relationship between them?

Best Regards,

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos
deepak_dave2
Participant
0 Kudos

Hi,

The dates mentioned above is used for forward/backward scheduling for a said material.The item once processed in the order generates its own schedule line for delivery and thus creates a delivery schedule .

The dates mentioned are calculated based on the you manually entering the required delivery date and then it picks up the time duration in days which is stored in Customising.

And decides whether the order quantity can be delivered as per the date entered by you or it requires backward scheduling and hence proposes new qty or date.

Hope this helps .

Thanks

Deepak