Hi

I have created a new excel upload plan layout and profile to load plans by period. I have created this in our Dev system and this works fine. I have transported this to our QAS system and it uploaded the file without any errors, however on checking the plan it has only posted 1 period (period 7) for each line. Any Ideas?

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Ajay

Thank you very much for your help.

The file that I have created works in the DEV system and will post into each of the 12 Months/Periods, using 1 file. I have transported this to the QAS system and loaded the same file but this only enters 1 of the months/periods, the others do not seem to have been loaded.

Do you have any idea why the 2 clients would treat the file differently?

Thanks Jo

ajaycwa1981
Active Contributor
0 Kudos

Hi

The excel upload feature uploads only one file at a time.. Thats expected behavior..

You need to create different excel files for each period... In the MENU options, you would see the option to upload a file as well as upload a directory... You need to choose the Later...

SAVE all the files in a folder (directory) and give the folder path to upload the same

BR,Ajay M