Backflushing

Former Member
0 Kudos

Dear All,

If i want that system would not allow backflushing of a fert if its components are missing or short. how can i do this. thanks

Accepted Solutions (1)

Accepted Solutions (1)

sundaresan_velayudam
Active Contributor
0 Kudos

In OPK4, In individual Entry general tab, check the Goods movement tick & termination of incorrect goods movement. IF any components are Shortage while confirmation, system won;t allow to do confirmation

Former Member
0 Kudos

Dear Sundaresan . E. V ,

Thanks for ur reply but i m using repetitive manufacturing. so how can i restricts backflushing in case components are missing or short.

sundaresan_velayudam
Active Contributor
0 Kudos

In REM profile- In error correction for backflushing, Check the execute correction in dailog mode and set mandatory.

Check your scenario in dev, If it meets your reqmt , transport to PRD

Former Member
0 Kudos

Hi ,

Please check with this combination.

Create stock determination strategy with combination of stock determination rule & stock determination group. Assign this stock

determination rule in REM profile in control data 2.

Also assign stock determination group to the material master, in MRP 2 View. I hope this will work.

Regards,

Sandeep