on 01-28-2011 12:13 PM
Hi folks,
I have 5 sales order for the same product of quantity 2 each for different customers. Is it possible to create a single production order of 10 quantitiesfor these requirements. Please help on this.
Hi
If you are using the Strategy as 40
Your incoming sales order will reduce the Independent requirements
Your Planned Orders are based on the Independent requirements created
If the incoming sales orders qty. increases the independent requirement qty,
additional planed orders are generated by the system automatically to meet the demand of sales orders
Generated planed orders can be converted into production orders, irrespective of the sales orders receipt.
This consumption is based on the Consumption mode & consumption period that you will set in MRP3 view of the material master
Hope this will help you, for any other details , revert
Regards
BRS REDDY
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
This is not possible in standard SAP R/3 if MTO. If you are using the IS MILL DIMP Order combination functionality then you can combine the sales order.
Please refer this useful link,
http://help.sap.com/erp2005_ehp_04/helpdata/EN/cc/f3f2ae403c11d385c30000e8200b4c/frameset.htm
Yes in strategy 40 you can do this.
Regards,
R.Brahmankar
Edited by: R Brahmankar on Jan 28, 2011 6:30 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
What strategy group you are using for this material in the material master ?.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
68 | |
14 | |
8 | |
6 | |
5 | |
5 | |
5 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.