HUM Issue

Former Member
0 Kudos

Dear Gurus,

I'm new to HUM and Currently I'm working on HUM.I've created a material and a packaging material.I created a Purchasing document and taking inbound delivery for the Purchasing document and doing packing in inbound delivery.

I made the Putaway process for the material and doing MIGO respect to Inbound delivery.In MIGO system creates a delivery number when saving instead a material document on saving.

I don't the exact problem.System is not giving any error message in MIGO.

Can anyone share with me the thoughts on this issue?

Regards

PKB

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

As per my understanding the MIGO transaction does not support the packed inbound deliveries.

you need to do GR with VL32N then it will works.

Hope it helps you.

rgds,

Kris.

Former Member
0 Kudos

Hi Krishna,

As per your reply I've done that and it was working.

Thanks a lot for your suggestion and I'm struggling for one week for this issue and today I post in SDN for the answer.

Regards

Pranaya

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

I too had a similar issue.

I had the inbound delivery packed and TO was open.At this stahe I treid to do GR agaisnt Inbound delivery in MIGO. System created another Inbound Delivery ( since Sloc was HU managed).

So, you need to confirm TO in LT12 which means PGR is done or as suggested in the above post, do the GR in in VL32N after TO was confirmed

Regards

Former Member
0 Kudos

Hi Sashi,

Thanks for your reply.

As Krishna suggest me the same as you told, it's working.

Thanks a lot for your suggestion.

Regards

PKB

csaba_szommer
Active Contributor
0 Kudos

Very starnge issue.

Are you sure a delivery was created? Did you check purchase order history? What can you see?

Which paramters did you use in MIGO? A01 (Goods Receipt)-R04 (Inbound Delivery?

did you check the whether there's goods movement in MB51???