Hi All,

a)I want to create 25 Planned orders for material 'X' and each order with quantity of 1 each in a single plant. Is there a method through which we can have 25 planned orders created at a single shot or the only way is to create each planned order of Qty 1 individually?.

b) does we have a tcode for mass conversion of planned orders to production order?.

Please suggest me.

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Use LOT size as FX and Fix Lot quantity as 1 In mrp 1 view. Then put demand of 25 in MD61 and run MRP system will create 25 planned order then collectively convert these order through CO41.

Please try and come back.

Regards,

R.Brahmankar

former_member184595
Active Participant
0 Kudos

Hi Brahmankar,

Thanks for the explanation. I could able to create required number of Planned orders with the process mentioned by you.

I had awarded points to all the friends who has replied to my queries.

Thanks all.

Answers (4)

Answers (4)

former_member533946
Active Contributor
0 Kudos

Hi dear,

If the material is is having BOM then MRP will create planned order accordingly.

U can use CO41 to convert planned order into production order in mass.

Edited by: Deepak Kulkarni on Jan 27, 2011 6:19 PM

Former Member
0 Kudos

In the material master of this material in the MRP 1 View put minimum lot size and maximum lot size as 1. Now if the requirement is 25, system will create 25 planned orders of each qty 1 once you do the planning run

b) CO41

former_member184574
Active Contributor
0 Kudos

In the material master of this material in the MRP 1 View put minimum lot size and maximum lot size as 1. Now if the requirement is 25, system will create 25 planned orders of each qty 1 once you do the planning run. Hope this solves your issue.

Former Member
0 Kudos

a) there is no simple way . You should create manually these planned orders or eventually develop some basic program to make the creation automatic.

b) CO41