Required Quantity are not copy from BOM

Former Member
0 Kudos

Dear SAP GURU,

I encounter this situation when i try Convert Plan Order ---> PO , Or Try create Process Order Manully.

But the issue here , when i look into the Material component list , the quantity for all required quantity are "ZERO".

I suspecting the Table is locked and that's why when convert to PO is "ZERO".

Can anyone tell me how to investigate this issue please?

tq

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Unable to understand your query, can you upload some screenshots of what error you notice (i.e. process order, BOM, etc.) to some portal n paste the link here to have some understanding of the issue

Former Member
0 Kudos

Any SAP PP GURU here to help me investigate this issue ?