how do i customize a pricing condition?

Former Member
0 Kudos

currently i have a condition for calculating surcharge of 5%, as of now this condition is taking the amount from PB00 and calculate the 5% amount.

however, i have freight costs in the line item as well, how do i configure the surcharge condition so that the it will calculate from the actual price instead?since actual price is the total of gross price and freight value.

thanks.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Go to Define Calculation schema select your Pricing procedure

1 1 PB00 Gross Price X 9

1 2 PBXX Gross Price X 9

20 1 FRA1 Freight % 1 FRE FRE

30 0 Gross Total 1 20

40 1 Surcharge 30

41 0 Net Price 40

I think its helped you

Thanks

Rakesh

Former Member
0 Kudos

hi rakesh,

managed to find it myself already, anyway just by adding the '9' sutot for the freight condition type is enough already.

thanks for replying as well.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hii,

Create a statistical condition type in the Pricing which add up gross price and freight value, then calculate your surcharge on that statistical condition.

Regards,

Mohar

Former Member
0 Kudos

hi moharghosh,

would like to ask u some question regarding the Moving average price in material master.

under normal circumstance, the MAP is updated when there's GR being performed for the PO line item concerning the material price only.

how do i configure as such that when the GR is done, The freight costs are being factored in as well for the MAP price.

in case you are still unsure of what i am trying to say, pls see below

In material master, Current MAP $10, 5 qty in plant

PO A, 1 qty, material price is $16

after GR is posted the , the qty is now 6 and the MAP is now $11. (default setup)

lets say i am going to factor in the freight cost.

in material master, Current MAP $10, 5 qty in plant.

PO B, 1 Qty, material price $16, freight costs $5.

how do i factor in the freight costs to the MAP?

so that after GR is posted, the Qty is 6 and the MAP is (50165) / 6 ???