Jan 27, 2011 at 01:58 AM

Settlement Error : Message No. KD561

1931 Views

My client has the following requirement,

For Example,

Client has undertaken a million dollar project for a customer. It has encurred a cost (for example say $500k). The WBSE element used to caputre the cost is defined as Account Assignment as well as Billing element. The project reaches a certain milestone and the customer is send a invoice for a payment of $100K. We have assigned the same WBSE during the creation of Sales order and created the billing invoice of $100K. We are not using the milestone. The above cost is Expense and not to be captalized. The revenue received from the customer is to be booked against the cost incuured on the project. At the end of the month, we settle all the cost on the expense project to the Cost Center.

When I run CJI3 for that particular WBSE, following are the entires,

a.........Dr. 500K

b........Cr. 100K

Total Cost ...400K

At the end of the month, when I am trying to settle the WBSE to the cost center (in the settlement profile, CCtr is a valid reciever), it gives me the below error message,

"Settlmnt from revenues/debit-side down paymnts to receiver CTR 101500015 not allowed

Message no. KD561

Diagnosis

The sender has revenues or customer down payments with cost element 51810010 (business transaction: CO Through-postings from FI).

You cannot settle these revenues or customer down payments to receiver CTR 101500015.

Procedure

Change the settlement rule for the sender. It can be useful, for example, to use a source structure to settle costs and revenues separately to different receivers.

Note

Revenues or customer down payments can only be settled to G/L accounts, profitability segments, sales documents, real estate objects, orders with revenues, or WBS elements."

Any suggestion would be appreciated. Any suggestion for the alternative ways to perform the above scenarios.?

Regards,