Hi All,

I created one order, though stock was sufficient, it didnt confirmed the quantity. I changed the route and then it confirmed !

What is the logic for this ?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi,

please check shipping point calendar for the same.

please check and update

balajia

Former Member
0 Kudos

Hi Both,

I checked these basic configuration, its does not work. Any idea if any other logic fits ?

Former Member
0 Kudos

Yes, Normally, the routes determine the number of days required to reach out to the destination. Now, when you have a route that takes less time to reach out to the destination on time, then, system will alter the dates and give u a confirmed quantity. If the route takes more days and the goods have to leave your godown early, then, for that particular day, the qunatity may not be available. Or Visa Versa is also true. So, the sales order is confirming the quantity when you change the route.

It is like Material availability date+PickPack time + Loading time + Transportation time = delivery date to the customer. Transporation time changes with the routes.

Hope this helps...

Regards,

Mukund S

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Colleague,

In Stock Transport Order scenario, the good issue date should be

based on the Factory Calendar of the supplying plant, while delivery

date should be based on that of the receiving plant.

Please, check the configuration done in factory calendar.

I hope it can help you.

Regards

Ruy Castro