Purchase Requisition in opening period in MD02??

385 Views

Hello all,

i have material A with char :

- Procurement type X

- Sched Margin Key 000 (Op Period 10)

- Planned Delivery Time 10

Now, i have made PIR for 3 months, Jan - Feb - March 2011,

When i run the MRP run MD02 using Create PR with in opening period ('2'),

Why is in MD04 when i check the result, it makes 3 Planned Order, not Purchase Requisition??

Regards,

Marufat