on 01-25-2011 6:37 AM
Hello all,
i have material A with char :
- Procurement type X
- Sched Margin Key 000 (Op Period 10)
- Planned Delivery Time 10
Now, i have made PIR for 3 months, Jan - Feb - March 2011,
When i run the MRP run MD02 using Create PR with in opening period ('2'),
Why is in MD04 when i check the result, it makes 3 Planned Order, not Purchase Requisition??
Regards,
Marufat
Thank you all for the solutions,
So i just want to confirm that i have to make the Procurement Type to only "F" (cannot use "X") to get the Opening Period to be PR
Regards,
Marufat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
As Sundaresan states, with "X" SAP will always select "In House" as the preferred supply source. Change this to F and check again, running the MRP with the indicator "2" for Pur Req.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
i have material A with char :
- Procurement type X
- Sched Margin Key 000 (Op Period 10)
- Planned Delivery Time 10
Now, i have made PIR for 3 months, Jan - Feb - March 2011,
When i run the MRP run MD02 using Create PR with in opening period ('2'),
Why is in MD04 when i check the result, it makes 3 Planned Order, not Purchase Requisition??
My ans-With the above setting in Material Master,if you run MRP to get Purchase requisition in Stock/requirements list,you must have the settings like below-
The system checks the planning file
u2022The system calculates the net requirements for every material.
u2022The system calculates procurement proposals.
u2022Scheduling happens.
u2022The system determines the type of procurement proposals.
u2022During MRP run, the system checks some critical situations which need tobe worked manually and hence it creates exception messages.
So make sure you have procurement proposal as "F" or "X" and the "MRP control Paramers" are like-
pro key-NETCH
create purchase req-2
Schedule lines-3
create MRP list-1
planning Mode-1
scheduling-1
please do this and revert.
Regards
Chandra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
system will create a PR only for procurement type F, otherwise system will create a Plan order only for that setting
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
An opening period of 0 days means that, together with the indicator "Create req. order" from "2", purchase requisitions can be created only if the opening date is the same as the planning date.
Or if scheduling is carried out on a non-working day, the requirement date is set to a non-working day and the delivery date or start and opening dates are set to the previous working day.
As a result, the opening and planning dates no longer fall on the same day and the system generates corresponding planned orders only.
Please refer the OSS Note 206666 - MRP: Control parameters during planning
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check the Procurement Type in the MRP2 Tab of the Material Master.
Please maintain 'E' for Inhouse production, 'F' for External Procurement and 'X' for both.
Hope it helps.
Cheers,
Kaushik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.