Screen Personas - Note Checker behaving differently in DEV and Quality

Dec 09, 2016 at 12:20 PM

56

avatar image

We are on screen personas 3 SP03.

Early this week we moved the transport from DEV to Quality system for end user acceptance testing.

All these flavors are working fine in development system but many of them are giving scripting errors in Quality system.

So first thing we did was to run Note checker functionality via /personas/admin and development system shows that everything is green and all notes are upto date.

All these notes were also transported to Quality.

Though when we run the note checker functionality in Quality it shows many notes in red color and says "can be implemented". When we check SNOTE for these specific notes, SNOTE says that they can not be implemented in our system.

It all started with scripting errors in Quality and we ended up with this discrepancy in note checker between both systems.

Both systems are running on same Kernel level and also running same version of personas.

Not sure how to resolve these scripting errors in Quality system when they are working fine in development system.

Has anybody else experience similar issues?

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

5 Answers

Manoj Deverapalli Dec 09, 2016 at 12:49 PM
0

Hi Gurjeet,

You can try exporting flavors in Development and Import in Quality.

Share
10 |10000 characters needed characters left characters exceeded
Manoj Deverapalli Dec 09, 2016 at 12:52 PM
0

Is your Development and Quality on Same SP Level?

Share
10 |10000 characters needed characters left characters exceeded
Gurjeet Dhaliwal Dec 09, 2016 at 02:41 PM
0

HI Manoj,

Yes both Quality and development are on same SP level.

Even though transport request has moved all flavors and related resources to Quality, as per your suggestion i used the import option and imported the flavor in Quality system. But still same scripting error..

Share
10 |10000 characters needed characters left characters exceeded
Tamas Hoznek
Dec 09, 2016 at 05:22 PM
0

IF the notes Checker says in Quality that notes can be implemented but they in fact cannot, then this needs to be investigated. Open an OSS incident and provide access to both systems with reproducible examples of the script error.

Share
10 |10000 characters needed characters left characters exceeded
Gurjeet Dhaliwal Dec 09, 2016 at 08:31 PM
0

Thanks Tamas,

I did opened a message with SAP and they adjusted ITS notes in our Quality system.

And now both Development and Quality system are showing same log; though we are still getting scripting errors in Quality system.

Though to be honest i am not sure what they meant and what they meant when they said---------------------

"I went to your QA system and adjusted the ITS notes"...

I will ask them to explain in detail, so others can benefit from it.

Will update my message once i get more information.