Hi Friends,

In My Scenario there are 1000's of orders for a particular material which do not get processed for delivery by VL10A. However the delivery is created out of these orders when VL01N is used.

Probable reason is that the trouble material did not have loading group maintained when the orders were maintained.Is it true that T Code VL10A checks for loading group while VL01N does not???

But as there are 1000's of orders its not possible to do single delivery for them.

Is there is some Other way to do the delivery through ....anyone having solution??

Thanks ,

J Nagesh

Accepted Solutions (1)

Accepted Solutions (1)

Shiva_Ram
Active Contributor
0 Kudos

Without loading group, the system can't determine shipping point in the sales order. Hence check one of the sales orders line item ->shipping tab ->shipping point field. Shipping point is the basis and important criteria to select sales documents and further to create deliveries. When you say, in VL01N the user is able to create delivery, did they enter the shipping point first in the sales order line item level and then tried in VL01N?

If shipping point is missing in sales orders, then in VL10A, the system can't select the sales orders for further processing.

Regards,

Answers (1)

Answers (1)

Former Member
0 Kudos

hi nagesh,

loading group we cannot maintain at sales order level.

it flows from sales org 2 view of material master record.

please check with an abaper giving this program name to debugg RVV50R10_PRESTEP.

hope this clears your issue and update the forum

balajia