Hi everyone,

I'm working in a new implementation of SRM 7.0 in classic scenario with ECC Ehp4. We want to use the new functionality of Central contract and we have a pair of doubts:

- We want to create central contracts from an accepted bid (bid invitation and/or auction) or directly in manage contract. Our doubt: is a standard behavior create the central contract in SRM and distribute it in ECC or only it can be created in ECC? (We need the central contract in both systems)

- When we create a central contract in SRM, can we activate a WF and after the contract is approved the contract can be send to ECC?

- We have the following process:

  • A user create a SC

  • The SC is released and sent to SoCo

  • In SoCo we assign a contract to the SC

  • Finally, we press the option "create PO"

The doubt is if we can define a WF in SRM after we press the option create PO and before the PO is created in ECC?

We need your help!

BR,

Ivá