Hi experts,
we face following problem: heuristic creates purchase orders when there is no source of supply.
Background:
there is a forecast demand for a location product on a customer location without transport lane to the production plant due to false master data.
The SNP heuristic generates purchase requisitions to fulfill the demand and there is no requirements shortage.
So it is hard to recognize which forecast demands can't be fulfilled.
Is there a parameter in material master or in a heuristic profie which disables the creation of purchase requisitions in snp heuristic when there is no source of supply.
If no purchase requisition is created there will be a requirement shortage which can be recognised by an alert.
Thanks for your help.