CNS41 - Difference in planning work X amount of work per period

42 Views

Guys, good night

Would like help from you regarding a problem in SAP.

I have a project that I have a plan in operations tied to a work center.

Running CNS41 envision that the sum of jobs in operation totaled 184 hours in PEP father of operations. But when I check in CNS41, PEP father and ask that it appears that the detailed planning period, the total amount distributed during the months of planning add up to only 124 instead of 184 HOAs hours.

I've done the search for SAP notes, but found nothing.

Has anyone had a problem like this?

Does anyone know if there is any note to be applied to correct the value in the period detailed CNS41?

Thanks and I look forward to assist you.