Dear Friends,
I updated the COPA plan data through KEPM by using planning layout,It created the document number 10380623 on Jan,19th.Later my busines asked to load some more line items, when I post through the KEPM on Jan 20th(using the lay out which I used earlier),some crazy data have been posted with document number 10380624 with negative and positive amounts for all my first data load combination, moreover there is no data load happend for my second set of data load.
Then I used the Transaction KE1C and delete the data posted on Jan 20 by using the selection option " Creattion Date " now all reversal posting done for my Jan 20 th load.So, now My Jan19th data laod is fine.
Now, am scaring to load my addition data as it will again screw my Jan 19 th data.
Could some one advice the best approch to tackle this, is there any way I can manually push the data as my second data laod is not much (just 10 lines). Correct me where am doing wrong.
Thanks in advance,