Hi,
I have a question regarding the settlement rule for an internal order. I have issued an internal order number to capture costs for a construction project. When the project is completed how do I update the settlement rule for the internal order to several assets all for different amounts?
For example an internal order number has collected costs of 150,000.00 for the completion of a building. When the building is complete and I want to do a final settlement of the internal order. I have one asset for land improvements for 43,000, another asset for the HVAC system for 33,000 and building costs of 74,000. When updating the settlement rule I know to create the assets and update the settlement rule with these asset numbers, but I am unclear on how to assign multiple assets with differnt amounts.