Jan 20, 2011 at 03:45 PM

RESB Number Range Object

1248 Views

Hi All,

There was an issue while converting Planned Order to Production Order. There was a warning message stating that the Number ********** for object RESB is in critical range. As a temporary solution, I changed the warning % from 10 to 5 and reset the number range buffer. Warning message did not appear after that.

Now I am trying to add a new number range to RESB. I created a new interval using T Code SNRO and assigned the new range to the specific plant using t code OPPQ. I reset the number range buffer as well.

When I create a Planned Order, the system still picks up the number from the predefined number range. Am I missing something

Regards

Ashish