Hi,
when I try to assign external service on historical order by entering control key PM03 for operation, system shows an error message "No service package in historical order. Reset Control Keys" or in detail
"No service package in historical order: Reset control keys
"Message no. IW143
Diagnosis
You have specified a control key for the service for an operation of this historical order.
This is not allowed.
System Response
Processing will not be continued.
Procedure
Change the control key."
I want to know
1- which settings are required to enable control key PM03 for this process?
2- is it possible to create reservations/requisition in historical orders?
3- can we calculate cost historical order cost in terms of stock/non stock material and external services?
Regards,