Hi Experts,
I have the below scenario:
We are using ps for customer projects.
1. I have 2 plants for my comp code 1000, say Plant A & Plant B,
2. Plant A creates and executes the projects, BOM is assigned to the wbs elements and MRP is run for the project.
3. Plant B supplies the required material to Plant A.
My Question is when I run MRP for the project in Plant A it should create the required planned order for Pant B, is this possible in SAP.
We are in SAP ECC 6.0 EhP 4.
Please clarify me, and let me know what are all the settings need to be done if yes.
Thanks and Regards,
Praveen